Rawalpindi Underpasses Reach 75% Completion Ahead of December Deadline

Rawalpindi district administration announced that two major underpasses at Race Course Park and Charing Cross have reached 75 percent completion and will open by December.

Share:WhatsAppX / PostFacebookLinkedIn
Rawalpindi Underpasses Reach 75% Completion Ahead of December Deadline — Newsbeat pakistan coverage
Rawalpindi Underpasses Reach 75% Completion Ahead of December Deadline — Newsbeat Pakistan Desk
Key Takeaways
  • The Race Course Park and Charing Cross underpasses are scheduled for completion by December.
  • Both projects are part of a 25-kilometer signal-free corridor connecting Koral Chowk with Motorway Chowk.

ISLAMABAD — The district administration has confirmed that construction work on two major urban underpasses located at Race Course Park and Charing Cross has advanced to 75 percent completion, with officials targeting a December launch. Executed by the Punjab Highway Department, these infrastructure initiatives form a critical component of the broader municipal strategy to streamline metropolitan transit and curb chronic congestion across major twin-city arteries.

According to project blueprints, the Race Course Park underpass features a specialized three-level road configuration designed with two dedicated lanes for northbound vehicular traffic. Meanwhile, the Charing Cross site incorporates a two-level road arrangement outfitted with two underpass lanes tailored to manage southbound movement. Concurrently, field teams are executing comprehensive road rehabilitation and expansion between Bungalow No. 276 and Raffay Mall along Peshawar Road, alongside the systematic underground relocation of utilities to eliminate roadside bottlenecks.

These ongoing civil works are integral to a sprawling 25-kilometer signal-free corridor project engineered to link Koral Chowk directly with Motorway Chowk. The broader infrastructural blueprint encompasses the previously finalized remodeling of Kutchery Chowk and the construction of the General Post Office underpass. Additional complementary phases involve the National Highway Authority rehabilitating the stretch between Motorway Chowk and Chur Chowk, alongside the Rawalpindi Development Authority reconstructing Old Airport Road.

Upon full implementation, provincial authorities anticipate that the interconnected corridor will drastically slash travel times between the Islamabad Expressway and Motorway Chowk to a mere 15 to 20 minutes. With the entire multi-tiered project scheduled for ultimate delivery by June 2027, the ongoing December milestones mark a decisive operational step toward alleviating daily commuting pressures for thousands of motorists across the garrison city.